HYDROLINK NEWS I - 2016

Date:16. 9. 2016
28.jpg

SHIRATAKI project in Hokkaido  (Japan) in operation – 280 kW Horizontal Double regulated S Kaplan

 

Reconstruction of Shirataki small hydro power plant project took place from March 2015 to June 2016. The Buyer NIPPON KOEI Co. Ltd. Upgraded intake equipment, open channel and inlet building. Hydrolink was supplier of complete technology: inlet valve, kaplan turbine, hydraulic unit, generator and low voltage electrical part including control system. The site is located at Hokkaido island, Japan and the basic parametrs are:

H = 14 m

Hnet = 11,50 m

Q = 2,70 m3/s

Installed output = 280 kW

Assynchronous generator TES is directly coupled to the turbine shaft (757 rpm)

Inspection in the factory in Czechia


BORGONA HPP  NORWAY

 

The Borgona Hydro power plant in Norway is close to commissioning.

In this case Electrical part is supplied by the local company Ryfylke Elektro while

Pelton turbine HYDROHROM and TES generator are from Czechia.

Just before shipment in July 2016

 

HPP BORGONA

H = 350 m

Hnet = 330 m

Q = 700 l/s

Pt = 2 050 kW



 

Other items:

 
top
 
Hydrolink, s.r.o.
17. listopadu 984
252 63 Roztoky
Czech Republic
tel.:
+420 233 910 968
+420 233 910 969
fax.:
+420 233 910 970
© 2000-2009 Hydrolink s.r.o.
Turbines and Small Hydro Power Plants exporter
 
Webdesign a webhosting Saturn-Toya s.r.o.
Čeština